Communications - Scientific Letters of the University of Zilina 2022, 24(2):D72-D84 | DOI: 10.26552/com.C.2022.2.D72-D84

Causes for the Change Orders in Road Construction: Reviewed from Owner

Mega Waty ORCID...1, Hendrik Sulistio ORCID...1
Civil Engineering Program, Tarumanagara University, Jakarta, Indonesia

Changes in road construction are affected by the owner and contractor at the beginning, middle, or end of the project. This study aims to determine the ranking of the factors that cause change orders for road construction from the owner's point of view. Data was collected by distributing questionnaires and interviews to project owners. Reliability and validity tests involving 32 respondents resulted in 48 causes of change orders. This study quantifies the relative importance of the factors that cause change orders and shows the ranking of factors and groups that cause change orders according to their level of importance for causes of change orders. This goal is achieved through the analysis of the results of the interviews. According to the calculation of the Relative Importance Index (RII), all the factors and groups are ranked and the most significant ranking is determined regarding the causes of the change orders.

Keywords: rank cause change order, relative importance index, owner
Grants and funding:

This study was funded by the Ministry of Research and Technology, Indonesia. Therefore, the authors acknowledge the assistance and cooperation of the Ministry of Public Works and Public Housing and Public Works Service DKI Jakarta, Banten and West Java.

Received: October 6, 2021; Accepted: December 6, 2021; Prepublished online: January 26, 2022; Published: April 1, 2022  Show citation

ACS AIP APA ASA Harvard Chicago Chicago Notes IEEE ISO690 MLA NLM Turabian Vancouver
Waty, M., & Sulistio, H. (2022). Causes for the Change Orders in Road Construction: Reviewed from Owner. Communications - Scientific Letters of the University of Zilina, 24(2), D72-84. doi: 10.26552/com.C.2022.2.D72-D84
Download citation

References

  1. FISK, E. R., REYNOLDS, W. D. Construction project administration. 9. ed. Pearson, 2010. ISBN 978-0132866736.
  2. IBBS, W. Quantitative impacts of project change: size issues. Journal of Construction Engineering and Management [online]. 1997, 123(3), p. 308-311. ISSN 0733-9364, eISSN 1943-7862. Available from: https://doi.org/10.1061/(ASCE)0733-9364(1997)123:3(308) Go to original source...
  3. SERAG, E., OLOUFA, A., MALONE, L., RADWAN, E. Model for quantifying the impact of change orders on project cost for US roadwork construction. Journal of Construction Engineering and Management [online]. 2010, 136(9), p. 1015-102. ISSN 0733-9364, eISSN 1943-7862. Available from: https://doi.org/10.1061/ASCECO.1943-7862.0000206 Go to original source...
  4. ANASTOPOLOUS, P. C., LABI, S., BHARGAVA, A., BORDAT, C., MANNERING, F. L. Frequency of change orders in highway construction using alternate count-data modeling methods. Journal of Construction Engineering and Management [online]. 2010, 136(8), p. 886-893. ISSN 0733-9364, eISSN 1943-7862. Available from: https://doi.org/10.1061/ASCECO.1943-7862.0000198 Go to original source...
  5. WAMBEKE, B. W., HSIANG, S. M., LIU, M. Causes of variation in construction project task starting times and duration. Journal of Construction Engineering and Management [online]. 2011, 137(9), p. 663-677. ISSN 0733-9364, eISSN 1943-7862. Available from: https://doi.org/10.1061/(ASCE)CO.1943-7862.0000342 Go to original source...
  6. WATY, M. Analysis of change orders on road pavement projects / Analisa change order pada proyek perkerasan jalan (in Indonesian). STEMBI- Bandung Business School, 2013. ISBN 978-602-98733-4-4, p. 65-66.
  7. YANA, A. G. A., RUSDHI, H. A., WIBOWO, M. A. Analysis of factors affecting design changes in a construction project with partial least square (PLS). Procedia Engineering. 2015, 125, p. 40-45. ISSN 1877-7058. Go to original source...
  8. ALNUAMI, A. S., TAHA, R. A., MOHSIN, M. A., AL HARTHY, A. S. Causes, effect. benefit and remedies change order on public construction project in Oman. Journal of Construction Engineering and Management [online]. 2010, 136(5), p. 615-622. ISSN 0733-9364, eISSN 1943-7862. Available from: https://doi.org/10.1061/ASCECO.1943-7862.0000154 Go to original source...
  9. AKHAVIAN, R., BEHZADAN, A. H. An integrated data collection and analysis framework for remote monitoring and planning of construction operations. Advanced Engineering Informatics [online]. 2012, 26(4), p. 749-761. ISSN 1474-0346. Available from: http://dx.doi.org/10.1016/j.aei.2012.04.004 Go to original source...
  10. TAYLOR, T. R., UDDIN, M., GOODRUUM, P. M., MCCOY, A., SHAN, Y. Change orders and lessons learned: knowledge from statistical analyses of engineering change orders on Kentucky highway projects. Journal of Construction Engineering and Management [online]. 2012, 138(12), p. 1360-1369. ISSN 0733-9364, eISSN 1943-7862. Available from: https://doi.org/10.1061/(ASCE)CO.1943-7862.0000550 Go to original source...
  11. SHRESTA, P. P., SHRESTA, K. K., KANDIE, T. K. Effects of change orders on the cost and schedule of rural road maintenance projects. Journal of Legal Affairs and Dispute Resolution in Engineering and Construction [online]. 2017, 9(3), 04517010. ISSN 1943-4162, eISSN 1943-4170. Available from: https://doi.org/10.1061/(ASCE) LA.1943-4170.0000227 Go to original source...
  12. HALWATURA, R. U., RANASINGHE, N. P. N. P. Causes of variation orders in road construction projects in Sri Lanka. International Scholarly Research Notices [online]. 2013. Available from: https//dx.doi.org/10.1155/2013/381670 Go to original source...
  13. DICKSON, O. D., GERRYSHOM, M., WANYONA, G. Variations in civil engineering construction projects in Kenya: causes and effects. International Journal of Engineering Research and Technology. 2015, 4(2), p. 1124-1129. ISSN 2278-0181
  14. HANNA, A. S., ISKANDAR, K. A. Quantifying and modeling the cumulative impact of change orders. Journal of Construction Engineering and Management [online]. 2017, 143(10), 04017076. ISSN 0733-9364, eISSN 1943-7862. Available from: https://doi.org/10.1061/(ASCE)CO.1943-7862.0001385 Go to original source...
  15. SHRESTA, K. K., SHRESTA, P. P. Change orders on road maintenance contracts: causes and preventive measures. Journal of Legal Affairs and Dispute Resolution in Engineering and Construction [online]. 2019, 11(3), 04519009. ISSN 1943-4162, eISSN 1943-4170. Available from: https://doi.org/10.1061/(ASCE)LA.1943-4170.0000299 Go to original source...
  16. WATY, M., SULISTIO, H. Identify the risk of road construction project change orders / Identifikasi risiko change order proyek konstruksi jalan (in Indonesian). Jurnal Muara Sains, Teknologi, Kedokteran dan Ilmu Kesehatan [online]. 2021, 5(1), p. 225-234. ISSN 2579-6402, eISSN 2579-6410. Available from: https://doi.org/10.24912/jmstkik.v5i1.10094 Go to original source...
  17. WATY, M., SULISTIO, H. Calculation of change orders for road projects in Banten / Perhitungan change order proyek jalan di Banten (in Indonesian). Jurnal Muara Sains, Teknologi, Kedokteran dan Ilmu Kesehatan [online]. 2020, 4(2), p. 211-220. ISSN 2579-6402, eISSN 2579-6410. Available from: https://doi.org/10.24912/jmstkik.v4i2.6342 Go to original source...
  18. BARRIE, D. S., PAULSON, B. C. Professional construction management. 3. ed. Civil Engineering Series. Singapore: Mc Graw-Hill Inc., 1992. ISBN 978-0070038899.
  19. EDWARD, P., WATY, M. Causes of change orders on road pavement projects / Penyebab change order pada proyek perkerasan jalan (in Indonesian). JMTS: Jurnal Mitra Teknik Sipil [online]. 2020, 3(1), p. 207-214. eISSN 2622-545X. Available from: https://doi.org/10.24912/jmts.v3i1.7012 Go to original source...
  20. WATY, M., SULISTIO, H. Calculation of change order for road projects in Jakarta. IOP Conference Series: Materials Science and Engineering [online]. 2020, 1007(1), 012001. ISSN 1757-899X. Available from: https://doi.org/10.1088/1757-899X/1007/1/012001 Go to original source...
  21. WATY, M., SULISTIO, H. Change orders and the risk of change orders on road projects in West Java / Change order dan risiko change order pada proyek jalan di Jawa Barat (in Indonesian). Paduraksa: Jurnal Teknik Sipil Universitas Warmadewa [online]. 2021, 10(1), p. 124-141. ISSN 2303-2693, eISSN 2581-2939. Available from: https://doi.org/10.22225/pd.10.1.2387.124-141. Go to original source...
  22. GARSON, G. D. Structural equation modeling, from statnotes: topics in multivariate analysis. 2009.
  23. NUNNALLY, J. C. Psychometric theory 3E. Tata McGraw-hill Education, 1994. ISBN 9780071070881.
  24. HAIR, J. F., BLACK, W. C., BABIN, B. J. ANDERSON, R. E., TATHAM, R. Multivariatedata analysis. Upper Saddle River, 2006. ISBN 9780130329295.
  25. HSIEH, T. Y., LU, S. T., WU, C. H. Statistical analysis of causes for change orders in metropolitan public works. International Journal of Project Management [online]. 2004, 22(8), p. 679-686. ISSN 0263-7863. Available from: https://doi.org/10.1016/j.ijproman.2004.03.005 Go to original source...
  26. SOEHARTO, I. Project management from conceptual to operational. Jakarta: Erlangga, 1995. ISBN 9794115789.[27 GILBREATH, R. D. Managing construction contracts: operational controls for commercial risks. Vol. 3. John Wiley and Sons, 1992. ISBN 05447159321.[28] FINKE, M. R. A better way to estimate and mitigate disruption. Journal of Construction Engineering and Management [online]. 1998, 124(6), p. 490-497. ISSN 0733-9364, eISSN 1943-7862. Available from: https://doi.org/10.1061/(ASCE)0733-9364(1998)124:6(490) Go to original source...

This is an open access article distributed under the terms of the Creative Commons Attribution 4.0 International License (CC BY 4.0), which permits use, distribution, and reproduction in any medium, provided the original publication is properly cited. No use, distribution or reproduction is permitted which does not comply with these terms.